Initial construction and MBM scandal ===
Beginning in 1970, the construction of the Columbia Point campus was the largest public capital construction project in the history of Massachusetts (exceeded only later by the Big Dig). The state government hired a single construction management firm, McKee-Berger-Mansueto (MBM), to supervise six other architectural firms and construction companies to complete the project by September 1973. The construction had multiple delays: the Boston Edison Company had not finished its electrical work, and because the site was a former landfill (that had only been closed since 1963), a concrete and brick substructure (where all of the campus mechanical systems would run conduits) undergirded by hundreds of driven piles needed to be constructed before the buildings, but pile driving released methane from the former landfill, requiring construction workers to halt production while each release of methane dispersed.
The Columbia Point campus was originally composed of five buildings …